Basslink Interconnector Is Back After Two-Month Outage
By Corinne Reichert, ZDNet
June 6, 2018
The Basslink Interconnector subsea cable has returned to service, the company has announced, after a two-month outage due to third-party damage to the cable sustained in April.
As of 5.45pm AEST on Tuesday, the wholesale energy portion of the cable was back up and running, Basslink said. The delivery of wholesale telecommunications had been unaffected by the latest outage.
“We are pleased to resume normal operations and would also like to thank our repair team for their hard work and commitment over the past weeks,” Basslink CEO Malcolm Eccles said.
“This incident is unrelated to the outage in December 2015 and the ongoing dispute with the state of Tasmania,” the company added.
Basslink had last month been forced to delay the return to service of the cable from May 31 to early June, citing “logistics and scheduling challenges beyond the control of Basslink”.
“Due to the highly specialised nature of the equipment needed for the repair as well as the time needed to source the required expertise, the repair is taking longer than expected,” Eccles said at the time.
At the end of April, Basslink had said it was “looking at every possible opportunity to expedite” the return-to-service date of May 31 after previously delaying the date from April 14 following third-party damage to the system “during the routine maintenance at a transition station in Victoria”.
“We have repaired a high-pressure system within a piece of equipment at the Victorian converter station. To return the interconnector to service, we require specialised expertise and equipment to be brought in to repressurise this equipment,” Basslink said in April.
“It is a highly technical exercise. The equipment was damaged by a third-party contractor during routine works. There is no damage to the cable itself.”
According to Basslink, it has “worked around the clock” with its manufacturing partners over the last week to formulate a repair and repressurisation process, as well as finding experts and equipment and working on logistics for carrying out the procedure.
The company also revealed in April that its dispute with the state of Tasmania will be referred to arbitration after the two were unsuccessful in resolving it during “without prejudice” meetings.
“Unfortunately, the dispute was not resolved, and has led to Basslink being notified by the state today that the dispute is referred to arbitration. Basslink intends to vigorously defend itself in the arbitration and continues to reserve all its rights in this matter,” it said.
“Basslink maintains its position that there is no proper basis for these claims.”